Tool 7 · Primavera P6

P6 schedule comparison

Compare two XER exports in detail: what was added, deleted or changed, how logic, calendars and float moved, and what changed on the critical path. Runs in your browser.

Free tools / P6 Schedule Comparison

Tool 7 · Schedule comparison

P6 Schedule Comparison

For schedulers, project controls managers and forensic delay analysts. Load a baseline and an updated schedule, see exactly what changed, review it, and build an editable comparison report. Everything runs in this browser.

How to use this tool
  1. Choose the baseline and the updated schedule. The baseline can be the approved baseline or any earlier update. Tables, charts and reports call the two files "Baseline" and "Updated schedule" unless you type your own titles in the "Title for this schedule" boxes. Use Swap if they are the wrong way round. If a file holds several projects, pick the one to compare.
  2. Check the validation summary, then run the comparison. It lists duplicate Activity IDs, missing tables or calendars and links to other projects, and shows which kinds of data each file holds.
  3. Review matches. Activities are paired by Activity ID. Where an unmatched activity on each side looks like the same work with a new ID, the tool suggests it; you confirm or reject. You can also pair two activities by hand, and undo either.
  4. Filter the changes. Each tab has the same filters: WBS, status, type, criticality, minimum movement, review status and search. Select an Activity ID to see both versions side by side.
  5. Inspect critical-path and float findings. Choose the basis (total float, the P6 longest-path flag or each file’s own definition). The Critical path tab draws the updated schedule’s critical activities against the baseline, and the other way round. "Total float & free float" lists how float moved on every activity. "Critical path change review" lists what was observed and what may have contributed.
  6. Add evidence and reviewer notes. Mark findings Reviewed, Requires investigation or Explained, and record your explanation and the records that support it.
  7. Customise and download the report. The Report tab builds a PDF with your title block, optional logo, chosen sections and commentary, plus Excel exports and a session backup.
  8. Read long programmes on the Gantt. Group activities by WBS level, or switch grouping off for a waterfall in start-date order, and set the timescale from daily to quarterly or yearly for projects that run for many years.

The built-in sample is a Fictional Demonstration Project: every activity, date, calendar and relationship is invented. No suitable pair of public schedules with verified reuse rights was available, so no real project data is used.

Comparing your own pair of XER files uses 1 run. Changing settings, matches and filters, and building reports for that pair, do not use more. The fictional sample pair is free and needs no account. What counts as a run?