Free tool · Primavera P6
P6 Project Performance Dashboard
Compare several P6 updates: earned value, cost and schedule indices, S-curves, forecast finish and WBS drill-down. Runs in your browser.
Free tools / P6 Project Performance Dashboard
Building a dashboard from your own XER files uses 1 run, so select all your updates together. The fictional sample is free and needs no account. What counts as a run?
Performance dashboard
About this sample: This dashboard uses fictional data created by SyncMAX for demonstration. The Harbourview LRT Extension does not exist: every activity, date, percentage and cost is invented. The sample is a baseline and 12 monthly P6 XER updates, January 2026 to January 2027. View the sample details and calculation notes.
Privacy note: Your XER files and project figures are processed in your browser. They are never uploaded to SyncMAX or third-party servers. To save a copy of your results, download the report to your computer.
Clearing removes your files and figures from this page. Nothing is kept in browser storage.
Earned value S-curve
Show the figures as a table
Planned versus actual progress
Show the figures as a table
Finish dates: baseline versus actual or forecast
Show the figures as a table
Forecast finish across updates
Activities and milestones in scope
Both outputs are created in this browser for the scope and dates shown.
How these figures were calculated
Formulas: SPI = EV / PV · CPI = EV / AC · SV = EV − PV · CV = EV − AC · VAC = BAC − EAC. Index values are computed from totals for the selected scope. A dash means an input is missing or a denominator is zero.
Sample data source
- Dataset
- Harbourview LRT Extension (fictional demonstration project), project ID FDP-LRT.
- Origin
- Created by SyncMAX with a script. It is not based on any real project, client file or employer schedule. Any resemblance to a real LRT project is coincidental.
- Files
- 13 Primavera P6 XER files: one baseline (data date 05 Jan 2026) and 12 monthly updates (01 Feb 2026 to 01 Jan 2027).
- Content
- 19 activities in 5 WBS elements, with planned dates, actual dates, physical % complete, and budgeted, actual and remaining cost.
- Units
- Canadian dollars (fictional amounts); dates as calendar dates; movement in calendar days.
- Personal data
- None. No names, emails or organizations.
- Use
- Free to download and use for learning and testing.
Download the sample pack (.zip)
The pack holds the 13 XER files, a README, and the expected figures for every update. Load the XER files in this tool to reproduce them.
Your data stays with you. Files and entries are processed in your browser. Nothing is uploaded to SyncMAX or anyone else.
Video
How to use the dashboard
Thirty seconds with the fictional LRT sample: read the indices, follow the S-curve, drill into the WBS, export, then load your own XER updates.
More free tools
Try another tool
Schedule Health Check
A DCMA 14-point assessment of an XER or our sample: score, findings, action plan and downloadable reports.
Open the toolFree tool · two minutesCritical Path Challenge
Three scenarios that test whether acceleration really moves the finish date. Good practice for PMI-SP and P6 users.
Open the toolFree tool · recordsDelay Event Record Builder
Write a factual record of a delay event, then print it or download an Excel sheet. Nothing is sent anywhere.
Open the toolFree tool · Primavera P6Milestone Movement Tracker
Compare two P6 updates and see which milestones moved earlier or later, and by how many days.
Open the tool