Two-minute critical path challenge
If you recover two weeks at one station, will the project finish earlier? Answer first, then see the driving path and float.
Free tools / Critical Path Challenge
Critical path challenge
If you recover two weeks at this station, will the project finish earlier?
Scenario
Score: 0 of 0
The schedule
Fictional transit schedule. Common working calendar: durations in working weeks (5-day weeks), project starts at week 0. All links are finish-to-start with no lag. Testing and commissioning needs both the station and the systems work complete.
The proposal: accelerate C Station fit-out to recover 2 weeks. Nothing else changes.
Current schedule (before recovery)
The bar chart is a visual summary; the activity list and the result text give the same information.
Float, driving paths and recovery are core to our Primavera P6 training and PMI-SP exam preparation.
Simplified teaching example: one calendar, finish-to-start links, no constraints, resources or risk. Real recovery analysis needs the full schedule.
Your data stays with you. Files and entries are processed in your browser. Nothing is uploaded to SyncMAX or anyone else.
More free tools
Try another tool
Schedule Health Check
A DCMA 14-point assessment of an XER or our sample: score, findings, action plan and downloadable reports.
Open the toolFree tool · Primavera P6Milestone Movement Tracker
Compare two XER updates. See every milestone that moved, by how much, and export to Excel.
Open the toolFree tool · recordsDelay Event Record Builder
Write a factual record of a delay event, then print it or download an Excel sheet. Nothing is sent anywhere.
Open the toolFree tool · Primavera P6P6 Project Performance Dashboard
Compare several XER updates: earned value, S-curves, forecast finish and WBS drill-down.
Open the tool