Free tool · Primavera P6
Quantitative Schedule Risk Analysis (QSRA)
PERT & Monte Carlo simulation. Understand schedule uncertainty, quantify completion risk and make better decisions. Runs in your browser.
Free tools / QSRA
Free tool · Schedule risk
PERT & Monte Carlo schedule risk analysis
Load a P6 XER, give the remaining durations a range, add risk events if you have them, and simulate. You get P50, P80 and P90 completion dates, schedule contingency and the activities that drive the uncertainty.
Each completed simulation on your own schedule uses 1 run, whatever the number of scenarios. The guided example is free and needs no account. What counts as a run?
Your data stays with you. Files and entries are processed in your browser. Nothing is uploaded to SyncMAX or anyone else.
Video tutorial
See the QSRA tool in use
An 85-second walkthrough recorded from the working tool with the fictional transit project. It has a caption track.
Plain-language guide
Understanding Quantitative Schedule Risk Analysis
What is QSRA?
Quantitative Schedule Risk Analysis uses probability-based modelling to estimate the range of possible project completion dates, instead of relying on one deterministic forecast.
What is PERT?
PERT uses optimistic, most likely and pessimistic duration estimates to represent uncertainty in individual activities. The traditional formulas, TE = (O + 4M + P) / 6 and σ = (P − O) / 6, are quick approximations. The simulation samples a Beta-PERT distribution and reports its exact mean and spread separately.
What is Monte Carlo simulation?
Monte Carlo simulation repeatedly samples uncertain activity durations and recalculates the schedule, to produce a distribution of possible project outcomes. Ten thousand iterations means ten thousand complete recalculations of the network.
What does P50 mean?
P50 is the completion date achieved or beaten in approximately half of the modelled simulations.
What does P80 mean?
P80 is the completion date achieved or beaten in approximately 80% of modelled simulations.
Why is P80 important?
P80 is often considered when selecting a more risk-informed planning date or evaluating schedule contingency. It is not automatically the correct contractual or management target for every project, and it is not a guaranteed date.
What is schedule contingency?
The difference between a selected risk-informed completion date and the deterministic forecast, measured on a clearly stated calendar basis. This tool reports it in calendar days and in working days of the completion milestone’s calendar.
Why does the critical path change?
Different activities experience different sampled durations, so paths that are not critical in the original schedule may become critical during simulation. That is why every iteration recalculates the whole network instead of following the original critical path.
What is the criticality index?
The percentage of simulations in which an activity is on a driving path to the completion milestone. An activity with float in the deterministic schedule can still have a high criticality index.
Why do results depend on inputs?
Simulation results are only as credible as the schedule logic, duration ranges, risk assumptions, correlations and calculation engine. A precise-looking percentile from poor inputs is still a poor forecast.
Glossary
- Deterministic date
- The single completion date from the schedule as planned, with no uncertainty.
- Three-point estimate
- Minimum, most likely and maximum duration for an activity.
- Beta-PERT
- A smooth distribution fitted to a three-point estimate that favours the most likely value.
- Iteration
- One complete recalculation of the schedule with one set of sampled durations.
- Percentile (P-value)
- The date that a given share of iterations finish on or before.
- Driving path
- The chain of activities and relationships that sets the completion date in one iteration.
- Spearman correlation
- A measure of how closely two quantities rise and fall together, based on their ranks.
- Common-cause risk
- One cause, such as weather, that affects several activities at once and makes them correlated.
- Random seed
- A number that fixes the sequence of random samples so a run can be repeated exactly.
- Convergence
- The settling of a percentile as more iterations are added.
Your Project Data Stays on Your Computer. All schedule analysis and Monte Carlo simulations are performed locally in your browser. Your Primavera P6 files and project information are not uploaded to SyncMAX servers.